Do you need to close out your permits at the end of your project?
It is important to close your permits as soon as construction is completed to avoid problems when selling or developing your property in the future.
Submit wastewater clearance holds by using the FDEP Wastewater Clearance form.
Keep in mind:
Complete the As-Built Checklist
Complete the CCTV Checklist
Email closeout@orlando.gov the following:
For large file sizes, email closeout@orlando.gov for submittal options.
After you submit your documents, we’ll email you a confirmation that includes your review due date. Due dates are typically set at 10 business days.
Review due dates, comments, and status can be found using the Permit Lookup tool.
Go to Permit Lookup
After your digital submittal has been reviewed and approved by all review disciplines, submit two hard paper copies of the following:
Submit via mail or drop off in-person at:
City of Orlando City Hall Permitting First Floor 400 S Orange Ave Orlando, FL 32801
Review due dates, comments, and status are available using the Permit Lookup tool.
Check Permit Lookup
Upon complete approval, the document hold will be removed and the final inspection can be scheduled.
Schedule Inspection