Project hours are 7 a.m. to 5 p.m. Monday through Friday. Work on Saturday may become necessary should adverse weather occur.
Please be advised that adverse weather or unforeseen circumstances may create delays increasing the duration of these projects.
Listed below are the locations and anticipated dates for these resurfacing projects taking place:
- Tivoli Chase Drive, between Heartland Street and Oak Crest Road
Tuesday, June 14 - Monday, June 20
- Lake Champlain Drive
Monday, June 20 - Friday, June 24
- Lee Vista Boulevard, between Narcoossee Road and State Road 417
Monday, June 27 - Friday, July 8